A Chesterfield Kitchen Remodel Goes After the Roof, Not Before
A kitchen remodel in Chesterfield is safer after the roof is done, since tear-off dust and leaks land on new cabinets and ceilings.
- Sheet
- A11
- Subject
- Storm record and statute
- For
- A homeowner after a storm
- Trade
- Roof repair, roof replacement
If you are planning a kitchen remodel in Chesterfield and the roof is near the end of its life, the order of the work matters more than most homeowners expect. A roof crew tears off old shingles, drops debris into the yard, and leaves the deck open to weather while the job is underway. Dust and water go wherever the house lets them. A kitchen with new cabinets, a fresh ceiling, and a new floor is a poor place for either to arrive unplanned. This page covers the sequence, the permit questions, and what to ask a roofer before you choose a start date.
Town roofing
Chesterfield sits in St. Louis County, where winters bring a steady run of freeze and thaw cycles. A roof that has been patched through several winters often shows its weak spots in the first hard freeze after a remodel begins, because the ceiling below has been opened and the attic no longer holds the air and moisture the way it did. Ice damming at the north eave is common on older roofs in this part of the county, and a kitchen that sits under a low eave can see water come through the ceiling if the deck is not dried in quickly after tear-off.
Hail season runs through spring and early summer. A remodel that starts in March can end up with a storm moving through the middle of it. An open roof over a half-finished kitchen is a bad place to be when a cell of hail or a hard rain arrives, because a blown tarp or a missed seam lets water reach the cabinets within minutes. Ask each roofer what the crew does when the forecast turns, and who makes the call to stop work for the day.
Permits are the next question. In St. Louis County, a re-roof and an interior remodel are usually handled as separate permit records, each with its own inspections. A roof permit covers the roofing work and its final inspection. A kitchen remodel may need its own permit if it touches electrical or plumbing, such as moving a range, adding a vent through the roof, relocating a sink drain, or changing a circuit for new lighting. Ask which permit desk covers your address, whether the roof permit will close before the cabinets arrive, and who pulls each permit. A passed roof final is a dated record of the repair, and it is worth keeping with your house papers even when nobody asks for it.
The sequence that works in most Chesterfield homes is roof first, then the interior. Tear-off dust settles into the attic, drifts through the ceiling joints, and finds its way into the kitchen through can light openings and exhaust fan housings. Stacks of plywood, nail boxes, and bundle wrap are not what you want waiting on a new floor. Even careful work can knock loose a drywall or plaster edge along an outside wall, and a crew working above a kitchen can crack a ceiling that was sound the week before. Damage found while the roof is open is cheaper to repair before the cabinets and countertops are set.
The exception is a kitchen that needs work above the ceiling line, such as a new vent stack, a relocated exhaust duct, or a chimney chase opened through the roof. In that case the kitchen plan and the roof plan should be drawn together on one sheet, because the roofer needs to know exactly where a new penetration will land and the remodeler needs to know how the roof will be flashed around it. Writing both plans down before either crew starts is the only way to keep a flashing detail from falling between two contracts.
What it costs
Keys Roofing does not publish a flat price for a kitchen-and-roof sequence, because the scope depends on the roof's size, its pitch, its layer count, and what the kitchen work touches above the ceiling. What you can do is ask each roofer to separate the roof itself from any interior protection and repair. If the roof bid includes a line for protecting the kitchen, such as plastic sheeting over cabinets and counters, a drop cloth under the attic hatch, and a daily cleanup at the end of each workday, you can compare that line directly against the remodeler's price. If the roof bid says nothing about the kitchen at all, ask for that answer in writing before you sign.
The costs that show up when a roof and a kitchen overlap are usually the ones nobody writes down. A second round of ceiling repair after a leak is one. Removing and resetting upper cabinets so a crew can reach a wall is another. A return visit from an electrician, when a can light has to move because a rafter sits in its path, is a third. None of these should be a surprise if you ask about them before the first nail is driven. Each one is a line the roofer or the remodeler either owns or hands back to you, and the written answer tells you which.
Here are the lines to look for on any roof bid for a home with a kitchen remodel planned:
- A protection line for the kitchen during tear-off, with the materials named rather than described as protection
- A dust control step, such as sealing the attic hatch and the return vents before the first shingle comes off
- A named party who repairs any ceiling or drywall the roof crew disturbs, and the price or the rule for that repair
- Whether moving a cabinet, appliance, or light fixture is included in the roof price or left to you
- Who pulls the roof permit, who schedules the final inspection, and who pays any re-inspection fee
Compare the answers from each roofer against the same list. A bid that names one line clearly and leaves four others blank is not cheaper than a bid that names all five, even when its total is lower. The blanks are where the later bills come from.
What to ask
Put these questions to each roofer in writing, and ask for the answers before you pick a start date. A written reply gives you something to hold against the crew's actual work, and it gives the kitchen contractor a fixed point for their own schedule.
- Which day does the roof start, and what is left open to the weather overnight if the tear-off runs past the afternoon?
- Where will the crew stage shingles, underlayment, and debris, and does that spot block the kitchen's delivery door or the route to the back patio?
- Who seals the attic hatch and the return vents before tear-off, and who checks them at the end of each workday?
- If a leak appears in the kitchen ceiling during the job, who calls it in to whom, and who schedules the repair?
- Which permit does the roof work pull, which desk issues it, and when does the final inspection happen relative to the remodeler's cabinet delivery?
- Which Atlas or Malarkey shingle line goes on the roof, and can you see a sample on your own house before the order is placed?
Ask the kitchen remodeler the same questions from their side. Find out when they need the roof to be dried in, when they need the ceiling opened or closed, and whether they will accept a roof crew's word that the deck is dry. Two contractors who are working from different start dates will each assume the other one is responsible for the gap, and the written schedule is the only record that settles the question afterward.
If you want the roof scope in writing before you order cabinets, call the Keys Roofing office at (314) 220-2333 and ask for the protection line, the permit owner, and the start-day plan to be written onto the bid before you sign it.