A Solar Array on a Chesterfield Roof Needs Its Own Reset Calendar
A solar array has to be shut down, unmounted and recommissioned around a reroof, and the bid should name who books each step.
- Sheet
- A11
- Subject
- Storm record and statute
- For
- A homeowner after a storm
- Trade
- Roof repair, roof replacement
If your Chesterfield home has a solar array on the south or west slope, the reroof is not only a shingle job. The panels, the racking under them, the wiring that runs down the wall and the inverter on the wall all have to be taken apart and put back, and the electrical side has to be shut down before a roofer lifts a single tab near it. Most bids mention the array in one line. Few say who books the disconnect, who unbolts the racking, who reinstalls it, or who tells the utility the system is back on. This page is for the homeowner who has a quote in hand and wants those answers before the start date is set.
Who owns the array on your roof
Start with the paperwork. A solar array on a Chesterfield house is usually owned outright by the homeowner, leased from a solar company, or bought through a power purchase agreement. The owner of the equipment is often not the person who signed the roofing contract, and that difference decides who must approve the removal. A lease or power purchase agreement may require the solar company's own technician to do the disconnect and the reset, and it may bill a fee for that visit. Read the agreement for the words removal and reinstall before you agree to any roof date.
Your electric utility is the second party to check. Ameren Missouri is the electric utility for most of the Chesterfield area, and a grid-tied system runs under an interconnection agreement with that utility. Many homeowners forget that the utility needs to hear about the disconnect and again when the system is restored, because the reconnection is the step that lets the array run again. The roofer does not sign for the utility. The homeowner or the solar installer does, and the bid should say which one.
What the reset actually involves
The reset is a sequence, and each step has a different person responsible for it. The system is first shut down at the inverter and at the disconnect switch, and the panels stay idle until someone confirms the wiring is dead. The modules are unclamped from the rails, then the rails are unbolted from the mounting feet. Each mounting foot passes through the shingles into a rafter, so every foot is a penetration that needs new flashing and sealant once the roof is laid back down. A reset that leaks usually leaks at a foot, which is why the flashing count belongs in writing.
After the new shingles go on, the racking is reinstalled on the new flashings, the modules are clamped back, and the wiring is checked by someone qualified to energize it. Depending on how the wiring was changed and whether the panel was touched, the city may also want an electrical permit alongside the roofing permit. A roofer can pull the roofing permit. The electrical permit belongs to the electrician, and in some cases to the solar installer, so ask who pulls it instead of assuming.
Three dates that need names
A solar reset has three dates, and they do not fall on the same day. The first is the disconnect date, when someone switches the array off and the roof crew is allowed to work near the wiring. The second is the reset date, when the racking and modules come off the roof and tear-off can begin. The third is the restore date, when the array is recommissioned and the utility confirms it may run again. A roofer controls the first two. The third depends on the solar company, the electrician and the utility, and a roofer who promises it is promising more than they control.
Ask each roofer to write all three dates into the schedule, with a name beside each one. A blank in the restore row is the usual gap. Homeowners often find out the array is still off weeks after the roof is finished, because no one was assigned to make the call.
Lines to check in each bid
- Who removes the modules and the racking, and whether that work sits in the roofing price or is billed by the solar company
- How many flashed mounting feet the bid assumes, and whether that count matches the rail layout on the roof
- Who disconnects the system and who energizes it again, by name and phone number
- Whether an electrical permit is needed, and who pulls it
- Who notifies the utility at disconnect and again at restore
- Where the modules and rails wait while the roof is open, and who answers if one is damaged
- Whether the warranty on reinstalled racking is written separately from the roof warranty
Freeze and hail timing in the St. Louis area
The calendar matters more with a solar array because the work depends on dry, mild days. Racking bolts and sealant need temperatures the product data sheet allows, and a freeze during the reset can leave flashing set on a surface that will not bond. Hail season, which around St. Louis runs strongest in spring and early summer, is a second reason to plan the reset before the roof stays open for long. A bare deck under a removed array has no protection from a storm that arrives mid-afternoon, and modules are glass that can crack if they are dropped or struck while stacked on the ground.
If the roof has to stay open overnight while the array is off, ask the roofer what covers the deck and the open mounting holes. Ask whether the modules are stored under cover on the property or taken off site, and whether the rails stay on the ground or go up to the roof. The answers belong on the page you sign, not in a phone call.
What to hold in writing before the start date
Keep one sheet with the array details: the number of modules, the rail count, the inverter make and the location of the disconnect switch. Photograph the array from the ground and from the attic before anyone touches it, and date the photos. That record is what you will need if a module cracks during the reset or if the restored system does not produce the way it did before. A roofer can document the roof and every penetration. The solar company documents the array.
When you compare quotes, mark each roofer's answer to the lines above as yes, no or not yet. A blank counts as an answer too. If one bid prices the reset and another leaves it out, the gap is not a saving. It is a cost that will show up later, billed by someone else. Chesterfield Roof Replacement and Repair, the desk run by Keys Roofing, can answer the roofing side of these questions in writing. The office number is (314) 220-2333. Ask for the reset sequence and the flashing count before you pick a date.